I-205 Abernethy Bridge Project: Looking Ahead to 2024
Stepping into 2024 presents the ideal opportunity to summarize the anticipated developments that will likely occur this year as ODOT continues making steady progress widening and seismically upgrading the Abernethy Bridge.
Stepping into 2024 presents the ideal opportunity to summarize developments likely to occur this year as ODOT continues making steady progress widening and seismically upgrading the Abernethy Bridge. Scheduled for completion in 2025, the I-205 Abernethy Bridge Project is ODOT’s most significant highway construction project in over four and a half decades and will be the Portland region’s first earthquake-ready highway bridge across the Willamette River. Accomplishing this goal means 2024 will be another busy year for this monumental project.
Here are some of the critical milestones that are likely to occur during the year:
Continued construction of new bridge support columns
A key component of making the Abernethy Bridge earthquake ready is constructing new support columns to carry the bridge's weight across its entire length. When the new columns are completed, the old columns must be dismantled. This is a complicated process while the bridge and the river underneath the bridge remain open for traffic. 2024 will see crews continuing to build the new support columns that became visible to casual observers in 2023, and crews will remove components of the previous bridge support infrastructure as they are made obsolete by newly constructed elements. The new columns and other bridge support components are one of the project’s most innovative aspects and will be the focus of a future article.
Sound wall construction near southbound Exit 9 in Oregon City
This year, crews will construct a new sound wall near exit 9 alongside southbound I-205. The impacted residents voted on this sound wall following a comprehensive project noise analysis. This new sound barrier is designed to reduce the audible impact of I-205 in the immediate area.
Widening the I-205 bridge across Main Street in Oregon City
With the need to widen the segments of I-205 on either side of the Abernethy Bridge, crews will also widen the I-205 bridge that goes over Main Street in Oregon City.
As always, dates can shift, but 2024 will see work progress on various pieces of this critical and exciting project. Thank you for your continued patience and support, and we look forward to sharing regular updates about the I-205 Abernethy Bridge Project throughout this year.
Please sign up for text messages and email alerts to stay informed of road closures, detours, and other impacts, or visit TripCheck. You can also follow ODOT's Facebook, Instagram, and Twitter for updates on the I-205 Abernethy Bridge Project.