Construction updates and project timeline

Updated: July 24, 2026

Regional construction impacts

Construction noise in West Linn

Over the next couple of months, there is demolition work planned in West Linn on the north and south side of I-205. Crews are working to remove the concrete deck of the former elevated on-ramp from OR 43 to I-205 north. This ramp was replaced with the new roundabout that opened in 2023.

Crews will also be removing the elevated on-ramp itself along with the columns below the I-205 southbound off-ramp to OR 43. Most of the work will happen during the day, but some of the work will continue into the night.

Nearby residents and businesses may hear noise from this demolition work. Use the 24/7 noise hotline to report any noise concerns: 503-276-7809.

As with any construction project, closure dates and timing are subject to change due to weather or other unforeseen events. Please continue to check back for ongoing updates.

The next overnight directional closures of I-205 southbound are planned for July 31 and August 1.

The I-205 Abernethy Bridge is in the midst of a series of overnight directional closures this summer as crews pour concrete on the newly-widened bridge deck. These closures will either be northbound or southbound but not both directions at the same time. This work depends on dry weather and necessary prep work, and schedules may change or shift on short notice.

The next overnight closures of I-205 across the bridge are in the southbound direction and are currently planned for Friday, July 31 and Saturday, August 1.

Details of the July 31 and August 1 nighttime directional closures:

  • Overnight directional closures of I-205 southbound across the Abernethy Bridge (between OR 99E and OR 43) Friday, July 31, and Saturday, August 1, from 11 p.m. to 7 a.m. both nights 

  • The following on-ramp will also close both nights:

    • OR 99E on-ramp to I-205 southbound from 10 p.m. to 8 a.m.

Local and Regional Detours

  • Southbound traffic can bypass I-205 in this section by using detours on I-5, I-84 and the Ross Island Bridge.

  • Local traffic can use the Arch Bridge to cross the river.

  • Northbound I-205 lanes will remain open.

Additional overnight closures on I-205 south are planned on Friday, August 7, Saturday, August 8, Friday, August 14, and Saturday, August 15. Southbound overnight closures will continue in August.


Temporary construction impacts

I-205

  • Nighttime closure of I-205 southbound across the Abernethy Bridge on the following dates (see detour maps in section above):

    • Friday, July 31, and Saturday, August 1, from 11 p.m. to 7 a.m. both nights.

  • The ramp from OR 99E to I-205 southbound will also close on the following dates:

    • Friday, July 31, and Saturday, August 1, from 10 p.m. to 8 a.m. both nights.

  •  Nighttime northbound lane closures on the following dates:

    • Monday, July 27, through Thursday, July 30, from 10 p.m. to 5 a.m. each night.

  • Nighttime southbound ramp closure to OR 99E (Exit 9) on the following dates: 

    • Friday, July 24, from 10 p.m. to 7 a.m. 

    • Monday, July 27, through Thursday, July 30, from 10 p.m. to 5 a.m. each night. 

Detour map for southbound ramp closure to OR 99E (Exit 9)


OR 43

  • Nighttime northbound ramp closure to I-205 on the following dates (see detour map):

    • Monday, July 27, through Thursday, July 30, from 10 p.m. to 5 a.m. each night.

  • ‍Nighttime southbound lane closures on Monday, July 27, and Tuesday, July 30, from 8 p.m. to 5 a.m. both nights (see detour map).

Detour map for ramp closure to I-205 northbound

Detour map for OR 43 southbound closure


Main Street

  • Daytime flagging on Main Street in Oregon City Monday, July 27, through Friday, July 31, from 7 a.m. to 5:30 p.m. each day.

West Linn Park Trail

  • The West Bridge Trail will be closed 24/7 as crews work overhead.

Ongoing construction impacts

Traffic

  • OR 43 northbound single lane closure with trucks leaving and entering the highway.

  • Clackamette Drive single lane closure with temporary signal and flagger.

  • Jon Storm Park parking lot under the Abernethy Bridge closed during construction.  

  • Local roads will experience lane closures and traffic restrictions during construction.  

Noise

  • People who live and work in the project area will hear noise from construction equipment and vehicles, pile driving, bridge demolition, and other construction-related noise sources. 

  • 24/7 Noise Hotline: 503-276-7809. This number is available for nearby residents and businesses to help resolve any ODOT noise-related concerns 24 hours a day. 

  • For more information see project noise study »

Light

  • Stationary lights with low lumens will be placed in the river to alert boaters.

River

  • The Willamette River remains accessible during Abernethy Bridge construction; the Sportcraft Boat Ramp is open.

  • 'No wake' zones are in place during 2024 through the bridge construction area on the Willamette River. 

  • River users will notice several large barges anchored in the river and are required to stay 200 feet away from them. River users are urged to use extreme caution, and all boats must travel between the green and red buoys. 

Bike and Pedestrian

  • Bike and pedestrian routes through construction zones are in place. People walking and riding a bike need to use caution when traveling through the project area. Follow signs and stay alert.

  • OR 43 and OR 99E bike and pedestrian access restrictions.

Transit

  • No impacts.

Local Businesses

  • Remain open during construction.

Watch to learn about recent project developments.

Video of television interview with project leaders.

Project timeline 

Construction began in the summer of 2022 and is expected to conclude in 2027.