Construction updates and project timeline

Updated: June 28, 2026

Regional construction impacts

Construction noise in West Linn

Over the next couple of months, there is demolition work planned in West Linn on the north and south side of I-205. Crews are working to remove the concrete deck of the former elevated on-ramp from OR 43 to I-205 north. This ramp was replaced with the new roundabout that opened in 2023.

Crews will also be removing the elevated on-ramp itself along with the columns below the I-205 southbound off-ramp to OR 43. Most of the work will happen during the day, but some of the work will continue into the night.

Nearby residents and businesses may hear noise from this demolition work. Use the 24/7 noise hotline to report any noise concerns: 503-276-7809.

As with any construction project, closure dates and timing are subject to change due to weather or other unforeseen events. Please continue to check back for ongoing updates.

June 27 overnight directional closures of I-205 northbound is complete. The next one is planned for July 10

The I-205 Abernethy Bridge is fully open between OR 99E and OR 43 after last night's (Saturday, June 27) closure in the northbound direction for crews to pour concrete on the newly-widened bridge deck

This was the first in a series of overnight directional closures of the I-205 Abernethy Bridge this summer as crews continue pouring concrete on the bridge deck. These will either be northbound or southbound but not both directions at the same time. This work depends on dry weather and necessary prep work, and schedules may change or shift on short notice.

The next two overnight closures of I-205 northbound across the bridge are currently planned for Friday, July 10 and Saturday, July 18.

Details of the July 10 nighttime directional closure:

  • Overnight directional closure of I-205 northbound across the Abernethy Bridge (between OR 99E and OR 43) Friday, July 10, from 11 p.m. to 7 a.m. 

  • The following on-ramp will also close:

    • OR 43 on-ramp to I-205 northbound. 

Local and Regional Detours

  • Northbound traffic will bypass I-205 in this section by using detours on I-5 and I-84.

  • Local traffic can use the Arch Bridge to cross the river.

  • Southbound I-205 lanes will remain open.

An additional nighttime closures of I-205 northbound across the bridge is planned on July 18.


Temporary construction impacts

I-205

  • Nighttime closure of I-205 northbound across the Abernethy Bridge on Saturday, June 27, from 11 p.m. to 7 a.m. The ramp from OR 43 to I-205 will also close (see detour maps in section above).

  • Nighttime northbound lane closures on the following dates:

    • Monday, June 29, through Wednesday, July 1, from 10 p.m. to 5 a.m. each night.


OR 43

  • Nighttime ramp closure to I-205 northbound on the following dates (see detour map):

    • Monday, June 29, and Wednesday, July 1, from 10 p.m. to 5 a.m. both nights. 

Detour map for northbound ramp closure to I-205


West Linn Park Trail

  • The West Bridge Trail is temporarily closed as crews work overhead. We expect the path closure to continue 24/7 for the next several weeks.

Ongoing construction impacts

Traffic

  • OR 43 northbound single lane closure with trucks leaving and entering the highway.

  • Clackamette Drive single lane closure with temporary signal and flagger.

  • Jon Storm Park parking lot under the Abernethy Bridge closed during construction.  

  • Local roads will experience lane closures and traffic restrictions during construction.  

Noise

  • People who live and work in the project area will hear noise from construction equipment and vehicles, pile driving, bridge demolition, and other construction-related noise sources. 

  • 24/7 Noise Hotline: 503-276-7809. This number is available for nearby residents and businesses to help resolve any ODOT noise-related concerns 24 hours a day. 

  • For more information see project noise study »

Light

  • Stationary lights with low lumens will be placed in the river to alert boaters.

River

  • The Willamette River remains accessible during Abernethy Bridge construction; the Sportcraft Boat Ramp is open.

  • 'No wake' zones are in place during 2024 through the bridge construction area on the Willamette River. 

  • River users will notice several large barges anchored in the river and are required to stay 200 feet away from them. River users are urged to use extreme caution, and all boats must travel between the green and red buoys. 

Bike and Pedestrian

  • Bike and pedestrian routes through construction zones are in place. People walking and riding a bike need to use caution when traveling through the project area. Follow signs and stay alert.

  • OR 43 and OR 99E bike and pedestrian access restrictions.

Transit

  • No impacts.

Local Businesses

  • Remain open during construction.

Watch to learn about recent project developments.

Video of television interview with project leaders.

Project timeline 

Construction began in the summer of 2022 and is expected to conclude in 2027.