Construction updates and project timeline

Updated: Nov. 13, 2026

Regional construction impacts

I-205 north closed across the Abernethy Bridge the weekend of Nov. 20-23.

Over the weekend of November 20-23, all lanes of northbound I-205 across the Abernethy Bridge will close to allow crews to slide the northbound side of the bridge by around eight feet onto newly widened support piers. Read more about this process we call a 'bridge slide'. The closure will begin Friday, November 20 at 10 p.m. and end on Monday, November 23 by 5 a.m.

Closure details

Weekend closure of northbound I-205 across the Abernethy Bridge (between OR 43 and OR 99E) starting Friday, November 20 at 10 p.m. to Monday, November 23 at 5 a.m.

The following I-205 northbound ramps will also close for the weekend:

  • OR 43 on-ramp.

  • 10th Street on-ramp.

  • Stafford Road on-ramp.

Local and Regional Detours

  • Northbound traffic will bypass I-205 in this section by using detours on I-5 and I-84.

  • Local traffic can use the Arch Bridge to cross the river.

  • Southbound I-205 lanes will remain open.

Drivers should plan ahead, follow posted detour signs and allow extra travel time. Crews will be working 24/7 during the closure. Neighbors should expect construction activity and some daytime and nighttime noise throughout the weekend. Work could be postponed with strong winds in the forecast. 

A second weekend closure will take place a few weeks later on southbound I-205 while crews slide that side of the bridge. We will share confirmed dates and additional details before that work begins. The closure will not take place on a major holiday weekend. 

Maps for informational purposes only. Maps not to scale. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Construction noise in West Linn

Our contractor continues to work on the West Linn side of the Abernethy Bridge and on OR 43. The work is concentrated in the day as much as possible but nighttime work also occurs and may include noise. There is a higher amount of nighttime work in West Linn right now.

When doing night work, we asked the contractor to finish any work that exceeds the ambient (non-construction) noise levels by midnight. During those times, there may be work that continues beyond midnight but doesn’t exceed ambient levels. This includes the use of back-up alarms.

There are some cases when noisier work will go beyond midnight. We expect intermittent noisier work beyond midnight in the coming weeks.

 If you have questions or concerns related to construction noise, we're here to listen. Call the 24/7 noise hotline at 503-276-7809.

Temporary construction impacts

I-205

  • All northbound lanes on the Abernethy Bridge closed from Friday, Nov. 20, at 10 p.m. through Monday, Nov. 23, at 5 a.m. (see local and regional detour maps) 

  • Stafford Road and 10th Street northbound on-ramps will also be closed Friday, Nov. 20, at 10 p.m. through Monday, Nov. 23, at 5 a.m.   

Detour map for Abernethy Bridge closure and Stafford Road and 10th Street on-ramps

Detour map for Northbound Abernethy Bridge closure

  • Nighttime north and southbound lane closures will occur on the following dates: 

  • Monday, Nov. 16, through Thursday, Nov. 19, from 10 p.m. to 5 a.m. each night.  

  • Nighttime northbound off-ramp closure to OR 99E (exit 9) will occur on the following dates:  

  • Monday, Nov. 16, through Thursday, Nov. 19, from 10 p.m. to 5 a.m. each night. 

  • Friday, Nov. 20 at 10 p.m., through Monday, Nov. 23, at 5 a.m.

  • Nighttime southbound off-ramp closure to OR 43 (exit 8) will occur on Monday, Nov. 16, through Thursday, Nov. 19, from 7 p.m. to 5 a.m. each night. (see detour map) 

Detour map for southbound off-ramp closure to OR 43 (exit 8)


OR 43

  • Nighttime southbound directional closure will occur Monday, Nov. 16, through Thursday, Nov. 19, from 8 p.m. to 6 a.m. each night. (see detour map) 

  • Nighttime on-ramp closure to I-205 northbound will occur on the following dates:  

    • Monday, Nov. 16, through Thursday, Nov. 19, from 10 p.m. to 5 a.m. each night. 

    • Friday, Nov. 20, at 10 p.m. through Monday, Nov. 23, at 5 a.m.

Detour map for southbound OR 43 closure


West Linn Park Trail

  • The West Bridge Trail will have daytime closures the week of Oct. 26 and users will have to take an alternate route.

Ongoing construction impacts

Traffic

  • I-205, OR 43 and OR 99E lane and ramp closures.

  • Clackamette Drive and Main Street lane closures.

  • Jon Storm Park parking lot under the Abernethy Bridge closed during construction.  

  • Local roads will experience lane closures and traffic restrictions during construction.  

Noise

  • Noise Levels in West Linn »

  • People who live and work in the project area will hear noise from construction activities. 

  • 24/7 Noise Hotline: 503-276-7809. This number is available for nearby residents and businesses to help resolve any ODOT noise-related concerns 24 hours a day. 

  • For more information see project noise study »

Light

  • Stationary lights with low lumens will be placed in the river to alert boaters.

River

  • The Willamette River remains accessible during Abernethy Bridge construction; the Sportcraft Boat Ramp is open.

  • 'No wake' zones are in place during 2024 through the bridge construction area on the Willamette River. 

  • River users will notice several large barges anchored in the river and are required to stay 200 feet away from them. River users are urged to use extreme caution, and all boats must travel between the green and red buoys. 

Bike and Pedestrian

  • Bike and pedestrian routes through construction zones are in place. People walking and riding a bike need to use caution when traveling through the project area. Follow signs and stay alert.

  • OR 43 and OR 99E bike and pedestrian access restrictions.

Transit

  • Intermittent, short-term impacts to bus stops and routes.

Local Businesses

  • Remain open during construction.

Project timeline 

Construction began in the summer of 2022 and is expected to conclude in 2027.